1st
glimpse of 8,700-foot runway
Warwick
Beacon Online
Thu,
Jun 07 07
Written
By JOHN HOWELL
Although
the Rhode Island Airport Corporation voted only last week to examine a
shorter-than-9,350-foot option to extending Green’s main runway, consultants
studying airport improvements have already drafted drawings of the proposal and
will be able to address questions about it at a June 14 meeting.
“We’re
very encouraged to update everyone and to be as responsive as we can,” Carol
Lurie said Tuesday. Lurie, project manager for consultants Vanasse
Hangen Brustlin, Inc., will
discuss the two runway options under consideration – a 9,350-foot and an
8,700-foot version – at the meeting at the
But
city officials are questioning the value of conducting the meeting when little
information on the 8,700-foot alternative is available. Both City Planner Mark Carruolo and principal planner William DePasquale
suggest postponing the meeting so that the city and residents have the chance
to study the shorter runway extension plan.
“They
[VHB] should have all the answers for all the people and if they’re not
prepared to give answers they shouldn’t have it,” DePasquale
said. Carruolo called the meeting a “half meeting”
because there would be answers on the 9,350-foot proposal and not the shorter
alternative.
“We
can’t say what the impacts are,” Lurie said of the shorter runway option
explaining consultants are now in the process of conducting those studies.
Nonetheless, those attending the meeting will get a good picture of how the
runway could be configured as well as the impacts of improving the safety areas
of the shorter Runway 16-34. That runway, sometimes referred to as the
“crosswind runway,” wouldn’t be lengthened. But extending the safety zones to
comply with Federal Aviation Administration standards would require substantial
wetlands alterations.
“We
will explain what we are looking at and how we arrived at where we are,” Lurie
said of the presentation. The presentation will include cost estimates and
numbers as to the potential numbers of aircraft and passengers that would be
affected by each of the alternatives.
A
longer Runway 5-23, which is now 7,166 feet, is seen as essential if Green is
to offer airlines the capability of offering nonstop service to the West Coast.
VHB has calculated a 9,350-foot runway would enable about 90 percent of the
fleet now serving Green to reach West Coast destinations without refueling. A
shorter runway would place fuel and hence load limitations of aircraft thereby
reducing the numbers of passengers that could be served.
A
8,700-foot runway, however, does not dramatically restrict fleet usage.
Both
proposed runway extensions are predominately to the north, which comes as a
surprise since an extension to the south impacts less wetlands and it was
assumed RIAC and the FAA would seek to avoid any action requiring Warwick City
Council approval. As the law presently stands, RIAC would need Army Corps of
Engineers and Department of Environmental Management permits to alter wetlands
with final approval coming from the council.
What
has killed a southerly extension of the runway is the projected $112 million
cost of tunneling
The
new “deal breaker” could be Buckeye Brook.
The
9,350-foot alternative would require the relocation of the stream’s bed. The
8,700-foot version, however, leaves the stream untouched. Relocation of
Two
options are being considered so as to maintain
“This
is an important east-west artery for the city, a hurricane evacuation route,”
Lurie said.
Both
versions of a longer runway would require the realignment of
Lurie
said the added level of analysis required of the 8,700-foot option would add
about two months to the study process. She said she expects the final step in
the analysis – a record of decision from the FAA – would come in late 2008.
The
9,350-foot option would require the acquisition of 323 homes and 71 businesses
whereas the 8,700-foot version would mean the loss of 136 homes and 71
businesses. Most of the businesses affected are not in the path of Runway 5-23,
but rather are within the extended safety zone needed for Runway 16-34 and
clustered at the intersection of Post and Airport roads.
Responding
to suggestions that the June 14 meeting should be postponed, Lurie observed it
has been several months since the last informational meeting on proposed
airport improvements.
“It’s
important people understand what we’re doing,” she said.
Once
VHB has completed a 30 percent design of the 8,700-foot alternative, Lurie said
there would be more detailed information regarding what homes would need to be
taken as well as costs and environmental impacts. At that time another meeting
would be held.
In
addition to maps and information concerning runway alternatives and other
airport improvements, Lurie said RIAC and VHB staff would be available to
discuss the ongoing voluntary home acquisition program.